Q-2026-0165
Spyder Drill 40ft (12m) — assembly & PDI
Prepared by
Martin Monikainen
New build · created 25 Sept 2026
Valid until 25 Oct 2026
This quote is won and the job is released — lines are locked. Change scope on the job.
Labour
| Task | Work centre | Hours | Amount |
|---|---|---|---|
| Unpack & check kit | PDI & Dispatch | 8.0 | $1,080.00 |
| Assemble frame & dolly | Assembly | 58.0 | $7,830.00 |
| Fit openers — front rank | Assembly | 36.0 | $4,860.00 |
| Fit openers — rear rank | Assembly | 36.0 | $4,860.00 |
| Plumb hydraulics & coulter lift-out | Hydraulics | 40.0 | $5,400.00 |
| Wiring & lamps | Assembly | 8.0 | $1,080.00 |
| Paint touch-up | Paint | 8.0 | $1,080.00 |
| PDI & dispatch | PDI & Dispatch | 12.0 | $1,620.00 |
Parts & materials
| Item | Qty | Amount |
|---|---|---|
| K-Hart No-till Double Disc Opener — Model 4612KH-4612 | 48 | $90,960.00 |
| Parallel linkage arm set (spring loaded)KH-4612-PLA | 48 | $18,672.00 |
| K-Hart Press Wheel 13" — VT (V tyre)KH-PW-13VT | 48 | $10,800.00 |
| Press wheel arm & bracketKH-PW-ARM | 48 | $5,040.00 |
| K-Hart fertiliser coulter assembly 20"KH-CLT-20 | 24 | $21,240.00 |
| Dual caster dolly wheel assemblyTYR-CAST | 2 | $6,960.00 |
| Flotation tyre & rim 500/45-22.5TYR-500-22 | 4 | $6,760.00 |
| Hydraulic cylinder 3" × 8" — liftHYD-CYL-3x8 | 4 | $2,380.00 |
| Hydraulic hose 1/2" 2-wire (metre)HYD-HOSE-12 | 120 | $2,160.00 |
| Seed hose 1¼" (metre)SH-125 | 200 | $1,800.00 |
| Secondary head — 8 outletSH-MAN-8 | 6 | $2,790.00 |
| Hard-wired indicator lamp kitHW-LAMP-KIT | 1 | $320.00 |
| Steel, frame materials & consumables | 1 | $188,808.00 |
Direct Seeding & Harvesting Equipment Pty Ltd
ABN 41 064 712 880
978 Chester Pass Road, King River WA 6330
(08) 9844 3555 · sales@directseeding.com.au · directseeding.com.au
QUOTATION
Q-2026-0165
Date: 25 Sept 2026
Valid until: 25 Oct 2026
Prepared by: Martin Monikainen
Quote for
Hirsch Farming Co
Attn: Brendan Hirsch
Gnowangerup WA
ABN 77 068 512 417
08 9814 7090 · brendan@hirschfarmingco.com.au
Work
Spyder Drill 40ft (12m) — assembly & PDI
New build
| Description | Work centre | Hours / qty | Rate / unit | Amount ex GST |
|---|---|---|---|---|
| Labour | ||||
| Unpack & check kit | PDI & Dispatch | 8 | $135.00 | $1,080.00 |
| Assemble frame & dolly | Assembly | 58 | $135.00 | $7,830.00 |
| Fit openers — front rank | Assembly | 36 | $135.00 | $4,860.00 |
| Fit openers — rear rank | Assembly | 36 | $135.00 | $4,860.00 |
| Plumb hydraulics & coulter lift-out | Hydraulics | 40 | $135.00 | $5,400.00 |
| Wiring & lamps | Assembly | 8 | $135.00 | $1,080.00 |
| Paint touch-up | Paint | 8 | $135.00 | $1,080.00 |
| PDI & dispatch | PDI & Dispatch | 12 | $135.00 | $1,620.00 |
| Parts & materials | ||||
| K-Hart No-till Double Disc Opener — Model 4612 (KH-4612) | 48 | $1,895.00 | $90,960.00 | |
| Parallel linkage arm set (spring loaded) (KH-4612-PLA) | 48 | $389.00 | $18,672.00 | |
| K-Hart Press Wheel 13" — VT (V tyre) (KH-PW-13VT) | 48 | $225.00 | $10,800.00 | |
| Press wheel arm & bracket (KH-PW-ARM) | 48 | $105.00 | $5,040.00 | |
| K-Hart fertiliser coulter assembly 20" (KH-CLT-20) | 24 | $885.00 | $21,240.00 | |
| Dual caster dolly wheel assembly (TYR-CAST) | 2 | $3,480.00 | $6,960.00 | |
| Flotation tyre & rim 500/45-22.5 (TYR-500-22) | 4 | $1,690.00 | $6,760.00 | |
| Hydraulic cylinder 3" × 8" — lift (HYD-CYL-3x8) | 4 | $595.00 | $2,380.00 | |
| Hydraulic hose 1/2" 2-wire (metre) (HYD-HOSE-12) | 120 | $18.00 | $2,160.00 | |
| Seed hose 1¼" (metre) (SH-125) | 200 | $9.00 | $1,800.00 | |
| Secondary head — 8 outlet (SH-MAN-8) | 6 | $465.00 | $2,790.00 | |
| Hard-wired indicator lamp kit (HW-LAMP-KIT) | 1 | $320.00 | $320.00 | |
| Steel, frame materials & consumables | 1 | $188,808.00 | $188,808.00 | |
| Subtotal ex GST | $386,500.00 |
| GST 10% | $38,650.00 |
| Total inc GST | $425,150.00 |
Terms
All prices in Australian dollars. GST shown separately. This quotation is valid until 25 Oct 2026.
Payment terms: 30 days EOM. Goods supplied ex works 978 Chester Pass Road, King River WA 6330 unless freight is quoted above.
Build slot and delivery date are confirmed on acceptance. Variations to scope will be quoted separately before work proceeds.
Accepted by (name / signature / date): ______________________________________________
